Completion of steel structure erection of main unit of water-based resin phase II project of No.6 chemical engineering company of China
Hits: 3892547
2020-04-09
On April 3, the steel structure erection of the main unit of Wanhua chemical (Guangdong) water-based resin phase II project constructed by China Chemical Engineering Sixth Construction Co., Ltd. was completed. The project is located in Gaolan Port national economic and Technological Development Zone, Zhuhai City, Guangdong Province, with a total investment of 37.104 million yuan. The second phase of the water-based resin project is the expansion of the first phase of the water-based resin project. After being put into operation, the annual output of 100000 tons of green environmental protection water-based resin will be widely used in the production fields of coatings, adhesives, etc. China Chemical Engineering No.6 company has undertaken the civil engineering and installation works of the whole project.
The steel structure erected this time has a span of 30 meters from north to south, 90 meters from east to west, and a weight of 2200 tons. The top floor is 21.5 meters high, with four floors in total. The main crane of 350 tons truck crane and the tail of 50 tons truck crane are used for hoisting. Due to the outbreak, the project started nearly a month later than originally planned. In order to speed up the construction progress, China Chemical Engineering No.6 company optimized the construction scheme one week before the arrival of the steel structure, tested the safety performance of the tools and machines, equipped with beam carriers, and well conducted the safety education and training of the operators and safety technical disclosure; after the arrival of the steel structure, the company will measure the quality of the goods with the owner, the supervisor and the civil engineering party, and check the civil engineering foundation for compliance; The steel structure shall be prefabricated in batches, inspected in batches and installed with lifeline and cable wind rope to ensure the safety, quality and speed of construction.
As of April 7, China Chemical Engineering No.6 company has completed 1856 tons of steel structure splicing, steel grid laying, stair frame erection, 31000 dyne welding pipeline, 240 sets of equipment installation, and 62% of the total construction task, which lays a solid foundation for the realization of the project's production target this year.
Source: Sinochem new network